For most apartment buildings, hotels, offices, shops and industrial buildings in Goa, the fire NOC is one of the approvals that decides whether a project starts on time. It is issued by the Directorate of Fire & Emergency Services, Government of Goa in two stages, and the first stage, the initial NOC, is applied for with a questionnaire called Form I and a set of drawings.
This guide explains what Form I asks, which drawings it relies on, and the queries we see most often.
This is a general guide. The forms, fees and procedure are set by the Directorate and can change. Check the current requirements with the department or your consultant before you apply.
Two stages: initial and final
- Initial (provisional) NOC. Applied for before construction, with Form I and the drawings. The department checks that the building's layout and the proposed fire protection systems meet the requirements.
- Final NOC. Applied for when the building is complete. The department inspects and tests the installation against the approved drawings, and the building needs the final NOC before it is occupied.
The initial NOC is where most of the design work is checked, so it pays to get it right.
What Form I asks
Form I is a long questionnaire, around 44 questions, and almost every answer needs a cross reference to a drawing number. It falls into five groups.
1. The building and the site
Owner, address, the authority that approved the plans and its approval number, building name, height, plot area, number of floors, floor-wise built-up area, total built-up area, open area, occupancy and sub-occupancy, setbacks on each side, and what surrounds the site on the north, south, east and west.
These figures must match the architectural drawings exactly. A different built-up area on Form I and on the plans is one of the easiest ways to earn a query.
2. Fire tender access
- A clear passageway of at least 4.5 m for fire vehicles to enter the premises.
- A clear headroom of at least 5 m under any arch or covered gate.
- A hard surface around the building able to carry a fire engine.
These belong on the site plan, dimensioned, with the drawing number quoted on the form.
3. Construction and services shafts
Service ducts enclosed with 2-hour fire-rated walls, 2-hour inspection doors on the electrical shaft, shafts sealed at every floor with 1-hour fire-resistant material, glass facades on high-rise buildings, and whether the air conditioning and ventilation follow the fire code.
4. Means of escape
Two remote means of escape, the number and width of internal and external staircases with their treads and risers, 2-hour fire doors with panic bars, staircase pressurisation, a refuge area for buildings between 24 m and 39 m, a fire tower above eight storeys or 24 m, fire lifts on alternate power, two ramps for basement car parks, and basement smoke extraction.
5. Fire fighting and alarm systems
This is the part the fire protection designer prepares:
- Wet riser, downcomer or wet riser cum downcomer of at least 100 mm diameter.
- Landing valves of 63 mm on every floor with hose boxes and RRL hoses.
- Hose reels of at least 19 mm on every floor.
- Yard (external) hydrants of 150 mm where required.
- Water tanks: the underground and overhead fire water capacities in litres.
- Fire pumps: jockey, main electric, sprinkler and standby diesel pumps, with their duty.
- Fire brigade inlet.
- Fire alarm to IS 2189, with the panel in a control room or on the ground floor, manual call points and hooters at each staircase landing, and detectors suited to the occupancy.
- Automatic sprinklers where required, with their own tank and pump where needed.
- Signage to IS 12349 and extinguishers to IS 15683 on every floor.
- Lightning protection and barrier-free access.
The drawings that go with it
For a typical apartment building, the fire NOC set includes:
- Site plan showing fire tender access, the 4.5 m passage, hard surface and hydrants.
- Floor plans with staircases, exits, fire doors, refuge areas and travel distances (prepared by the architect).
- Fire fighting layouts for every floor: riser or downcomer, landing valves, hose reels, sprinklers and extinguishers.
- A fire fighting schematic from the tank and pumps to the top floor.
- Pump room and tank plan and sections.
- Fire alarm layouts and the alarm riser diagram.
- Calculations for the fire water storage, pump duty and head.
Every "Yes" on Form I should point to a drawing number where the item can be found.
The queries we see most often
- Figures that don't match. Height, floor count or built-up area different on the form, the plans and the calculations.
- No drawing reference. A "Yes" without a drawing number.
- Tank capacities that don't add up. Fire storage shown inside the domestic tank without a clear reserve, or a capacity smaller than the system needs.
- Pump details missing. Pumps listed without flow and head, or without the standby diesel pump.
- Escape routes unclear. Only one staircase, or staircases not remote from each other.
- Basements. No second ramp, no smoke extraction, or no sprinklers where the basement's size needs them.
- Code references. The form still refers to NBC 2016 and NBC 2005 clauses, while the national standard is now NBCS 2026. State clearly which basis the design follows.
Keeping it consistent
The simplest way to avoid queries is to fill in Form I from the same data used for the drawings and calculations. In our own workflow the building's floors, heights and areas, the fire requirements, the tank and pump calculations and the drawing register are held in one place, and Form I is filled from them, so a change to the drawings shows up on the form.
How we can help
IMI Design designs fire fighting and fire alarm systems and prepares the fire NOC drawings in Goa, including the Form I details, for apartment buildings, hotels, offices, shops and industrial buildings. For background on which buildings need which systems, read fire NOC in Goa: sprinklers, hydrants and fire alarms. Send us your architectural drawings and we'll confirm what your building needs.